AIS Applications



PPT -
Online Help


IMPORTANT:
The data entered and stored in the PPT system is non-contractual data used for the purpose of planning, resource and cost estimation only. The information held in PPT can in no way engage CERN's liability towards contractors, personnel, or any other party. Contractual data for suppliers remains under the control of FI & SPL divisions in the CERN financial system (Qualiac) whilst contractual data for members of the personnel remains under the control of HR division in the CERN HR database, which prevails.

EVM BASICS
EVM stands for Earned Value Management; a method for Project Managers to objectively measure the amount of work accomplished on a project or contract relative to the baseline plan, and to estimate total project costs and total duration of the project.

Planned Value (PV):
Example:
we have an 8 week activity with a 10KCHF budget linearly distributed. After 2 weeks, we have PV=10KCHF*2/8=2.5 KCHF.

The portion of work expected to be completed at a given date, times the authorized budget allocted to carry out that work. Amount of work scheduled measured as an estimation in CHF.
In former project management jargon, it is the budgeted cost of work scheduled (BCWS).

Earned Value (EV):
Example:
If the 8 week activity consists at manufacturing and delivering 10 magnets (linearly distributed), then when the 6 magnets are delivered: EV=10kCHF*6/10=6 kCHF.

The value of completed work expressed in terms of the budget assigned to that work.

Actual Cost (AC):
Example:
If when statusing you have paid 7 kCHF, these are your actual costs.

The costs actually incurred and recorded in accomplishing the work performed.

Budget at completion:
The total authorized budget for accomplishing the program scope of the work. In other words, it is the sum of the planned values at completion of the project.

Pre-requisites to setting up an EVM system

A clear scope of work is a pre-requisite for setting up such a system. A WBS (Work Breakdown Structure) is probably the best mean for doing so.

The WBS is a structured list of all the activities to carry out in order to complete a project. For each single activity, all the resources required (material, manpower, overheads...) must be identified and quantified. Allocated budgets should be based on these estimates. Short term activities are easier to estimate and schedule than long term activities; therefore EVM standards allow that long term activities remain agregated in planned packages with unallocated budgets.

The performance of the project, or sub-project, or of a single activity is measured using few indices:

Schedule variance (SV):
compares the actual physical progress (EV) to the planned one (PV): SV=EV-PV
If SV is negative, this means that the activity is behind schedule.
If SV is positive, the activity is ahead of schedule.
Example:
Using previous example, if 6 magnets are delivered at the end of week 6, then EV=6 kCHF and PV=7.5kCHF, then SV= -1.5kCHF

Cost variance (CV):
compares the actual costs (AC) to the actual physical progress, i.e the earned value (EV):.
CV=EV-AC
If CV is negative, this means that the budget tends to be overrun
If CV is positive, the budget tends to be underrun.

Using previous example, let's statusing at end of week 6:
• at that date, PV = 10 kCHF × 6/8 = 7.5 kCHF
• if 6 magnets are delivered at the end of week 6: EV = 10 kCHF × 6/10 = 6 kCHF
• if incurred expenditures are 7 kCHF, then AC = 7 kCHF.

SV = 6 kCHF - 7.5 kCHF = -1.5 kCHF < 0 activity is behind schedule.
CV = 6 kCHF - 7 kCHF = -1 kCHF < 0 the budget is being overrun!