BAANIV c4 MIGRATION PLANNING

Réunion du 30/05/2005


Présents: Artur Wiecek, Chris Lambert, James Purvis, Reinoud Martens, JL Doublet
Excusés: André Regelbrugge, Paul Smith
Absents:

Proposed date : friday 24 to sunday 26/06/2005

Proposed Schedule :

Date At Operation Estimated time
24/06/2005 12h00 Stop missc - Allow connection for bsp only
 
  12h05 Prepare bookclosing (job Arch) + cleaning data missc 1h30
  14h00 Delete table 400,410 misst
Delete Data Dictionary misst
Copy Data Dictionary missc->misst
0h30
  15h30 Export/import data base missc->misst 4h30
  21h00 Create runtime data dictionary misst 1h00
  22h00 Create tables 400,410 misst
Check tables
0h30
  22h30 Reorganize tables 400,410 misst 10h00
25/06/2005 08h00 Parameters modification
tests application
2h00
  10h00 Go - No go decision  
26/06/2005 ? Backup missc  
  ? Backup misst  
27/06/2005 04h00 Start production  

:

System people tasks :
-Stop access to missc and misst except for bsp (24/06– 12 O’clock)
-Backups missc/misst on 26/06
-Make synonym Baan4 point on misst (instead of missc)
-Baan gas bottles : the alias 'carbamail@tanks.cern.ch'goes to missc and should be changed to misst after the migration
-Network file system backup should not be scheduled for this w/end
-move aliases from missc to misst: BAAN4, STORESDB, BAANIVDB, TANKS
-move STORES DB from missc to misst
-test export/import stores database before migration
-write script for defragmentation Baan database

 


FLP tasks :
-Stop cron on missc (24/06 -12h00)
-install cron on misst
-Synchronize EDH + no EDH transfer after 12 O’clock on Friday
-install help files on the web server
-solve oracle optimization issue
-report remaining problems to Watermark ( Webtop messages, shared memory problem)
-Ensure of exITed (Baan consultancy)availability during the migration process

 

 