Go to CERN Home Page
Go to AIS home page

BAANIV c4 MIGRATION PLANNING

Réunion du 16/06/2005


Présents: Artur Wiecek, Chris Lambert, André Regelbrugge, Paul SmithJames Purvis, JL Doublet
Excusés: Reinoud Martens, Artur Wiecek
Absents:

Confirmation of migration date : friday 24 to sunday 26/06/2005

Proposed Schedule :

Date At Operation Who Estimated time
Before 24/06   Test restricted user access on misst system + FLP  
    ms-news to advise people of the baan unavailability FLP  
    test stores DB import/export system  
    ensure exITed availability during the w/end and ask for the new licence key FLP  
    Coordination with the EDH team + foundation FLP  
24/06/2005 11h55 Stop cron on missc FLP 1 mn
  12h00 Stop missc and misst - Restart without listener and allow connection for bsp user only - script to be provided by Artur to stop/start baan login
System 10 mn
  12h15 Prepare bookclosing (job Arch) transfer baan orders to qualiac + cleaning data missc FLP 1h30
  14h00

Delete table 400,410 misst
Delete Data Dictionary misst
Copy Data Dictionary missc->misst
sent a mail to system people : system ready for coalescing table space on misst

FLP 0h30
  14h15 Start stores bookclosing on m issc FLP 2/3 h 00
  14h30 Coalesce table space on misst System 10 mn
  14h45 Export/import stores database System  
  15h00 Change aliases for host names System  
  15h30 Export/import data base missc->misst FLP 4h30
  21h00 Create runtime data dictionary misst FLP 1h00
  22h00 Create tables 400,410 misst
Check tables
FLP 0h30
  22h30 Reorganize tables 400,410 misst FLP 10h00
25/06/2005 08h00 Parameters modification
tests application + set up cron on misst + launch some scripts to apply some generic updates (suppliers) load customers from cie 400 to cie 410.........
FLP 2h00
  10h00 Go -No go decision + Send a mail to system people to inform FLP  
  10h30 Test interfaces (foundation, EDH, Qualiac, FLP  
  14h00 Reactivate users on misst System  
26/06/2005 12h00 Backup misst System  
27/06/2005 04h00 Start production on misst Users  
  14h00 Backup missc (care with licence manager dependencies- missc should not be stopped) System  
week 27/06   Install new licence FLP  
mid july   install french version for Webtop + help files FLP  

:

Remarks :

-No system backup neither on missc nor on misst before sunday the 27th
-Network file system backup should not be scheduled for this w/end
-Never stop missc server (licence on misst is depending on missc server)





 

 


Displaying/Printing this page